Key Information:
- Phase 1 (3 March – 13 weeks): Rolling road closures & temporary lights on A2070 Kennington Rd & Silver Hill Rd. Silver Hill Rd closed (10 March – 2 weeks).
- Phase 2 (9 June – 7 weeks): Lees Rd & Silver Hill Rd closed to through traffic.
- Phase 3 (23 July – 7 weeks): A292 Hythe Rd closed, Lees Rd accessible via Silver Hill Rd.
Please check alternative routes before your visit.